Rouge, La. 225-916-2699 (Cell) 225-372-2869 (Home) E-Mail: dducote63@yahoo.com Summary of Qualifications Computer literate with full working knowledge
of most major spreadsheets, databases and word processing programs to include
all Windows applications. Scheduling
programs include, Primavera P3 Total Project Management Planning and
Controlling, Primavera P6 (currently version 8.2), MPAC (Maintenance Planning
and Control). Organize and plan all phases of industrial construction
including new construction, unit expansions, maintenance, and turnarounds. Employment History 6/14 to
Present: EXCEL Engineering, Gonzales, La. Senior
Maintenance/Project/Turnaround Scheduler Contracted to ConocoPhillips, Lost
Cabin Gas Plant, Lysite Wyoming · Create weekly schedules
from backlog using SAP. · Facilitate weekly and daily
schedule review meetings. · Update schedule daily and
issue updated schedule to supervisors. · Develop turnaround
schedules as well as project specific schedules using Primavera. 3/14 to 6/14:
Chicago Bridge & Iron Federal Services, Baton Rouge, La. Project
Controls Scheduler / Primavera Administrator · Provide detailed proposal
schedules for government projects. · Cost load schedules and
provide cost / revenue reports. · Acting primavera
administrator for Federal Services division. o Setting user security
privileges o Setting up calendars o Setting up resource
dictionary 6/13 to 2/14: EXCEL Engineering, Gonzales,
La. Senior
Project Controls Engineer for Methanex Chile Relocation Project, Geismar La. · Acted as owner’s rep to
oversee the general contractor’s project controls department. · Analyze contractor’s
schedule, earned value system FLA (field labor analysis) and compare to
reported weekly progress. · Make daily field walks to
review progress and compare against reported progress. · Attend weekly update and
schedule review meetings for all on site contractors to discuss manpower,
RFI’s, engineering solution’s, commercial issues, monthly payment invoices,
change orders, etc. · Attend weekly contractor’s
coordination meeting to discuss any potential conflicts among contractors. · Provided function
reliability reports from primavera to determine planned activities that were
scheduled to start or complete but failed to do so. Developed a constraint
profile for management to help mitigate road blocks to streamline field work. · Work closely with Methanex
SME’s (Subject Matter Experts) in the development of the system turnover
schedule. 3/10 to 5/13:
EnergySolutions, Salt Lake City, Ut. Senior
Project Controls Engineer for Zion Nuclear Facility, Decontamination /
Decommissioning Project, Zion, Il. · Lead scheduler for Zion D
& D restoration project. Mentored and supervised 4 on site primavera
schedulers. · Responsible for working
with SME’s (Subject Matter Experts) to develop detailed resource and cost
loaded schedule for reactor internals and reactor segmentation. Removal of
spent fuel from pool, construction of ISFSI (Independent Spent Fuel Storage
Installation) pad. · As a publically traded
company the project controls department provided earning forecast from
primavera for upper management to present to shareholders. · Provided primavera 12, 9,
and 3 week look ahead schedules for topic of discussion in weekly meetings. · Worked directly with the
work control group to add new activities, change logic to better represent
scheduled activities as field conditions changed. 11/08 to 2/10:
Jacobs Engineering, Houston, Tx. Project
Scheduler for ExxonMobil NRD Project, Baytown, Tx. · Responsible for scheduling
all construction activities for the ISBL (Inside Battery Limits) portion of
the project. · This includes duct banks,
foundations, structure steel, piping, equipment setting, electrical,
painting, and insulation. · Trend progress and analyze
weekly construction plans. · Develop forecast based on
remaining work and compare to FLA (Field Labor Analysis) progress reporting
tool. · Facilitated and provided
primavera 6 and 3 week look ahead schedules for topic of discussion in weekly
meetings. 09/08 to
10/08: Control Solutions Group Contracted to EnergySolutions, Salt Lake City,
Ut. Project
Scheduler for Zion Nuclear Facility, Decommissioning / Demolition
Project, Zion, Il. · Placed in charge of
building the large component removal schedules, containment building
demolition schedules, and waste water treatment schedule. · Project was put on hold due
to the down turn in economy in late 2008. 04/07 to
09/08: Pro Energy Services Contracted to Burns & McDonnell, Kansas City,
Mo. Project
Controls Manager for Westar Energy, Jeffrey Energy Center FGD Upgrade, St.
Marys, Ks. · Built master procurement /
construction schedule for the FGD project. · Maintained all sub projects
within the master schedule. · Built each contractors
progress curves based on their resource loaded schedule. · Monitor contractor’s
progress and schedule. · Analyze contractor’s weekly
construction scheduling plans and weekly schedule updates for comparison to
reported progress. · Develop with each
contractor, a schedule of values with an acceptable work breakdown structure
in sufficient detail to accurately monitor and approve contractor pay
applications (AIA Form). · Maintain a complete listing
of all “Field Work Authorizations”. · Attend weekly update
meetings and take meeting minutes, facilitate meetings in site manager’s
absence. 04/06 to
04/07: CDI Corp. Contracted to Dow Chemical Company, St. Charles Operation,
Taft, La. Planner/Scheduler/Project
Controls for Dow Chemical Emerald Project · Maintain master schedule
along with building a preliminary turnaround schedule with equipment
replacement/rework and with over 600 tie-in’s. · Monitor contractor’s
progress and schedule. · Analyze contractor’s weekly
construction scheduling plans and weekly schedule updates for comparison to
reported progress. · Facilitated weekly schedule
meetings to discuss three week look ahead schedule. · Ran Claim Digger software
to compare any changes from original to baseline schedules for management. 12/05 to
04/06: Pro Energy Services Contracted to Burns & McDonnell, Kansas City,
Mo. Planner/Scheduler/Project
Controls for Sinclair Refinery ULSD Project, Tulsa, Ok. · Prepare and maintain P3
schedules for upcoming HTU turnaround and facility expansion. · Provide manpower graphs and
reports, daily field look aheads. · Prepare rules of credit
reports for weekly update meetings. 03/05 to
12/05: Bronco Construction, Denham Springs,
LA Field
Engineer/P-3 Scheduler/Estimator for ConocoPhillips ULSD Project, Ponca City,
Ok. · Responsible for reviewing
and updating project orthographic and isometric drawings, field verifications
of elevations and coordinates. · Duties also include
distributing revised drawings to supervisors for changes that may need to be
made. · Set priorities on shop
fabricated pipe spools for completion and delivery to the field. · Submit various documents
which included Request for Information (RFI) and Proposed Change Orders
(PCO). · Prepared cost control
documents for supervisory and management personnel. · Completed as built piping
designs for field revisions and additions. · Estimate all phases of
mechanical, civil, structural take-offs and applied dollar amounts for
approval. · Developed and maintained
working daily P3 files for ongoing multi million dollar project expansions
and turnarounds. 10/01 to
03/05: Shaw Group, Baton Rouge, LA Maintenance
Planner/Scheduler/Estimator for Placid Refining LLC, Port Allen, La. · Duties consist of planning
and scheduling of daily maintenance work orders, which include machinery,
fixed equipment, piping, scaffolding, and carpenters. · Instrumental in preparing
pre-plans for equipment and PSV’s. · Worked closely with
Placid’s operator to prioritize work orders to be scheduled in highest
priority to minimize production loss or downtime. Managed work order backlog. · Also estimated and planned
Management of Change (MOC’s) and Approved Funding of Engineering (AFE’s)
changes. · Performed estimating of all
piping take-offs, material take-offs, and procured material to complete said
work orders. · Assigned to the Placid
Refining Company management team and performed duties that included
requesting bids for projects and the selection of sub contractors, also
tracked sub contractors work. · Performed as coordinator
for equipment and outside services. · Attend daily meetings with
management and supervision to discuss work progress. Education Certified
Pipefitting Instructor for Associated Builders and Contractors (ABC) National
Center for Construction Education and Research (NCCER) Awarded
Certificate of Completion Dow (Internal)
Primavera 5.0 Training Commint
Technical Services Planning &
Controlling With P3 E/C Enterprise Courses 102
& 106 Awarded
Certificate of Completion Commint
Technical Services, Inc., Planning &
Scheduling and Resource & Cost Analysis and Managing Project Data with P3
for Windows Courses 601,
602, 603 Awarded
Certificate of Completion Associated
Builders and Contractors (ABC) Planning/Scheduling Awarded
Certificate of Completion Associated Builders
and Contractors (ABC) Estimating Awarded
Certificate of Completion High School